More handling options at British Sugar
British Sugar’s plant at Bury St Edmunds has now completed
its campaign for improved systems for distributing granulated sugar,
following an extensive re-modelling programme by bulk handling specialist
Geo Robson & Co.
Valued at almost £¾ million, the project has increased
the flexibility of facilities for screening and delivering product
for bulk out-loading and bagging, and for re-circulating it back
into the factory.
Existing equipment – most of which was originally manufactured
and installed by Robson - has been modified and re-deployed wherever
possible. The company was also responsible for new structures, floors,
access platforms and stairways, and for demolishing and removing
redundant plant.
In the screening area, the process route has been simplified by
eliminating a number of elevators and extending the enclosed Robson
Cleanflo belt conveyor that brings sugar from the scalping screen.
Additional headroom to accommodate the new head end was provided
by raising the roof level by 4.5 metres.
The Cleanflo delivers product into a modified screw conveyor with
three outlets – an arrangement that allows the re-positioned
vibratory screens to be fed in any combination.
The screens separate the sugar into three grades - granulated,
granulated fines, and caster. Fines and caster are delivered into
separate holding bins to await further distribution, and the granulated
passes directly into bulk out-loading on a Robson Airglide enclosed
conveyor – a low-friction design that supports the carrying
belt on a cushion of air.
Belt and screw conveyors in the bulk out-loading area have been
configured so that each grade can be stored in any of the three
‘road bins’, as demand dictates.
Bin one is for internal movement by road tanker; bin 2 supplies
tankers taking product off-site; and bin three feeds the 50kg and
1tonne bagging lines. The final option is a route that returns granulated
to the factory, which is activated when all other outlets are closed
off.
Magnetic separators and metal detectors have been installed at
all critical points in the system. When a detector is activated,
a slug of sugar is run out into a one tonne bag at floor level for
inspection.
Stocks were built up to ensure that the plant could meet demand
during the July/August shutdown of the screening and out-loading
areas. Robson was allowed 16 days to install and commission the
granulated return system – the largest single item in the
project – and to position all the other equipment ready for
installation through to the end of August.
|